
Most office moves run on a lease date, not a furniture catalog. When the space is signed and the team starts in a few weeks, a factory order that takes over a month is not an option. This guide lays out how a Phoenix office can get as-new cubicles delivered and installed in about 2 weeks, what has to happen each week, and what to avoid.
- Your fast options
- The two-week plan
- What to have ready on day one
- Phoenix building logistics
- What happens on installation days
- Clearing the old office in the same two weeks
- What causes delays
Your fast options
Three grades can meet a short deadline. The right one depends on how the floor needs to look.
| Grade | Look | Typical timing |
|---|---|---|
| Pre-owned (liquidation grade) | Clean, normal wear, original finishes | As little as 72 hours |
| Hybrid | As new: new fabric, trim and worksurfaces on recycled panel cores | About 2 weeks installed, in most cases |
| Remanufactured | As new, wider finish choice | Usually 7 to 14 days to build, then install |
| New | New, full catalog | 4 to 6 weeks |
For most teams that want a new-looking floor on a real deadline, the hybrid workstation is the best fit. It is often around half the price of comparable new, and it uses in-stock fabrics so there is no wait on a mill. See what a hybrid workstation is for the details.
The two-week plan
Here is how a typical hybrid project runs from the first conversation. Larger floors and complex power add time, and your quote shows the actual dates.
Days 1 to 3: Layout and approval
- Send a floor plan, a landlord test fit or a measured sketch, plus your headcount.
- Receive a free space plan drawn to scale, with stations placed around columns, windows and doors.
- Confirm station size, panel height, glass, pedestals and the fabric and laminate colors.
- Approve the written quote. Delivery, installation and electrical are separate lines.
Days 4 to 10: Build
- Panel cores are inspected and re-covered in your chosen in-stock fabric.
- New worksurfaces are cut, hardware is refinished and new trim is fitted.
- Meanwhile, you confirm building access: elevator reservations, dock times and any certificate of insurance the building requires.
- Your electrician, or ours, confirms power feed locations.
Days 11 to 14: Deliver and install
- Parts arrive kitted and labeled by station.
- Crews build panels and connectors, then worksurfaces, storage and power.
- Electrical hookup and a final walk-through, with any punch-list items fixed before move-in.
What to have ready on day one
The fastest projects have answers to these questions in the first conversation:
- A floor plan or measured sketch, with columns, windows and doors marked.
- Headcount and roles, so station sizes match the work. The 6×6 guide covers the most common size.
- Power and data locations: where the wall, floor or ceiling feeds are.
- Building rules: elevator and dock hours, after-hours requirements, insurance certificates.
- Finish preferences: fabric color family, worksurface color, trim color.
- The move-in date, and whether a partial install would help.
Phoenix building logistics
Phoenix office buildings range from downtown and Midtown towers to suburban campuses in Tempe, Chandler, Scottsdale and the West Valley. A few local factors are worth planning for:
- Freight elevators and docks. High-rises often require reservations and limit hours. Book them as soon as the dates are set.
- After-hours work. Many buildings prefer installation in the evening or on weekends. That is routine and fits inside the two-week plan when booked early.
- Summer heat. From late spring through early fall, deliveries are best scheduled early in the day. The summer delivery guide covers this.
- Old furniture. If you are moving from another space, the same team can clear it. See office furniture liquidation in Phoenix.
What happens on installation days
Installation is where a good plan pays off. On a typical hybrid project the crew arrives with every station kitted and labeled to match the plan, so nothing is sorted on your floor.
- Protection first. Elevator pads, floor and door-frame protection go down before the first cart moves.
- Layout marked. Station positions are checked against the plan and the actual room, including columns and power feeds.
- Panels and connectors. The panel runs go up pod by pod, leveled and connected.
- Worksurfaces and storage. Corner pieces and returns are hung on their brackets, then pedestals are placed.
- Glass and trim. Glass stackers and finish trim go on last, so they are not damaged during the build.
- Power. Raceways or beltways are connected, and the building feed is hooked up by a licensed electrician where required.
- Walk-through. Every station is checked with you, and punch-list items are fixed before move-in.
- Clean-up. Packaging and debris leave with the crew.
Pods are often handed over one at a time, so a team can start moving in while the rest of the floor is finished.
Clearing the old office in the same two weeks
Many fast moves have two deadlines: the new space has to be ready, and the old space has to be handed back. Running both with one team removes a coordination problem. A typical sequence:
- Week 1: free walkthrough of the old space and a written recommendation for every piece, resale, donation, recycling or a mix, while the new floor is planned and approved.
- Week 2: new stations are installed, the team moves, and the old space is cleared and left broom-clean on the handback date.
Sometimes furniture from the old office is worth moving or reusing in the new one, and sometimes it is not. A walkthrough answers that before anything is ordered. See corporate relocation for how a combined move runs.
What causes delays
Two weeks is realistic in most cases. These are the things that push it out:
- Layout changes after approval. Moving a few stations is easy; changing sizes or heights restarts part of the build.
- Special-order fabric. In-stock colors keep the schedule. A custom fabric adds mill time.
- Late power decisions. Unknown feed locations can hold up the final hookup.
- Building approvals. A missing insurance certificate can stop a crew at the dock.
- Very large floors. More stations mean a longer build and install, often done in phases.
If the date cannot move, a phased approach works well: in-stock pre-owned cubicles go in first, and hybrid stations follow for the client-facing area.
To start a two-week plan, send your floor plan and headcount to hello@officestation.com or use the quote request form. Space planning is free, and every project is quoted individually.
Frequently asked questions
Can cubicles really be installed in 2 weeks?
Yes, in most cases. Hybrid workstations, built on recycled panel cores with new trim, refinished hardware, new worksurfaces and new in-stock fabric, are delivered and installed in about 2 weeks from an approved layout and fabric choice. The schedule depends on quantity, building access and power, and your quote states it up front.
What is faster than 2 weeks?
In-stock pre-owned, or liquidation-grade, workstations can be installed in as little as 72 hours in the Phoenix metro, depending on quantity and building access. They come in their original finishes with normal wear. Some teams install pre-owned stations first and switch a client-facing area to hybrid or remanufactured later.
What slows down a cubicle installation?
The most common delays are a layout that changes after approval, a special-order fabric, late answers on power locations, restricted freight elevator or dock hours, and building approvals such as certificates of insurance. Deciding these early, in the first few days, keeps a two-week schedule realistic.
Do I need an electrician for cubicles?
Usually, yes, for the final connection. Panel systems carry power through a base raceway or beltway, fed from a wall, floor or ceiling power pole. Connecting that feed to building power is done by a licensed electrician where your building or code requires it. Electrical is quoted as its own line.
Can cubicles be installed after hours in Phoenix?
Yes. Many Phoenix office buildings limit freight elevator and dock use during business hours, so installation is often scheduled for evenings or weekends. Tell us your building's rules early so the crew and the deliveries are booked into the right windows.
Which Valley cities do you install in?
Office Station installs across Greater Phoenix, including Phoenix, Scottsdale, Tempe, Mesa, Chandler, Gilbert, Glendale, Peoria, Surprise and Goodyear, and ships cubicles nationwide when a project needs it. Delivery and installation are quoted as separate lines, so you can see each part of the job.

