Short answer: Office Station, an office liquidation and decommissioning company in Phoenix, Arizona that works nationwide, plans most office decommissions over about 120 days from the first read of the lease to the landlord handback, while the physical removal of a typical floor with good dock access often takes only a few nights or a weekend. The total time depends on five things: how much furniture and how many workstations there are, how the inventory is routed (resale, donation or recycling), the building's elevator and dock rules, the IT and cabling scope, and what the lease says the space must look like at surrender.
- What decides how long it takes?
- How long does each phase take?
- How long does the removal itself take?
- Can it be done in 30 to 45 days?
- What makes a decommission run late?
- What should you do first?
What decides how long office decommissioning takes?
Clearing a floor is fast. The slow parts are the decisions and approvals around it. These are the factors that set the calendar, roughly in order of how often they matter:
| Factor | Why it changes the timeline |
|---|---|
| Headcount and furniture volume | More workstations, files and casegoods mean more inventory to grade, more truckloads and more removal nights. |
| How the inventory is routed | Resale, donation and recycling each have their own pickups. Donation depends on a recipient's schedule and capacity, so it is planned as one lane inside the larger schedule rather than the thing the date depends on. |
| Building access | Freight elevators and docks are shared and booked in windows. Towers often limit heavy moves to evenings and weekends and require certificates of insurance before any crew arrives. |
| IT and cabling | Network gear stays up until the last people leave. Devices need data wiping or documented destruction, and abandoned cabling comes out only after the network is down. |
| Lease return-to-condition terms | Broom-clean is common, but some leases add cabling removal, patch and paint, or restoring build-outs. Restoration has to fit between removal and the final walkthrough. |
| Internal decisions | Deciding what moves to a new space and what goes is often the longest single step. A named project owner keeps it from stalling. |
How long does each phase of a decommission take?
Counted back from the surrender date, a standard decommission falls into four phases. This is the same 120-day countdown laid out week by week in the lease-end move out timeline.
- Days 120 to 91: decide and inventory. Confirm the surrender date and the restoration and cabling clauses, name the team, decide what moves and what goes, and build an inventory with brands, counts and photos.
- Days 90 to 61: walkthrough and written recommendation. Contractors walk the space. Office Station typically schedules a walkthrough within 48 hours in Greater Phoenix and delivers a written recommendation within five business days, setting the route for each part of the inventory.
- Days 60 to 31: lock logistics. Submit certificates of insurance, reserve the freight elevator, dock and after-hours access, schedule IT shutdown, telecom disconnects and cabling removal.
- Days 30 to 0: execute and hand back. Employees clear personal items, IT pulls and documents devices, the crew removes furniture floor by floor, cabling and debris follow, restoration items are closed out and the space is walked with the property manager.
After handback, allow time to collect the closeout records: the itemized inventory, the diversion summary and certificates of data destruction for any electronics. Finance and sustainability teams usually need them.
How long does the removal itself take?
For a typical office floor with good dock and freight elevator access, the removal often takes a few nights or a weekend. In a tower, pace is set by elevator cycles and dock time rather than crew size, so the number of booked windows matters more than the number of people on the crew. Two steps are always sequenced in: hardwired panel systems are disconnected by a licensed electrician before take-down, and abandoned cabling comes out after the network is shut down, so the last week is not worked offline.
Partial floor give-backs take longer on the calendar, because the returned area is sectioned off and worked after hours while the rest of the office keeps running.
Can office decommissioning be done in 30 to 45 days?
Many offices can still exit cleanly with 30 to 45 days if decisions are made fast and the building cooperates. The way to do it is to run steps in parallel instead of in sequence:
- Read the surrender clause today and ask the property manager for the certificate of insurance requirements and move rules today.
- Request a walkthrough and send photos and a rough inventory ahead of it.
- Decide keep items within a week.
- Use one contractor for furniture, e-waste and cabling instead of coordinating three vendors.
- Book night and weekend removal so employees keep working to the end.
The lease-end date guide covers how to compress the plan when the countdown has already started.
What makes an office decommission run late?
- No single owner. Questions about what to keep sit for days that the schedule no longer has.
- Building access booked by someone else. Month-end is when other tenants move, and freight windows go first.
- Insurance paperwork. A certificate with the wrong holder wording can stop a crew at the dock.
- IT surprises. Leased copiers, carrier-owned routers and a forgotten server closet each have their own return or pickup.
- Restoration found late. Patch, paint and repair items discovered at the final walkthrough mean a second walkthrough.
The cost of running late is usually holdover rent and deductions from the security deposit, which is why the schedule is built backward from the surrender date, not forward from the day the work starts.
What should you do first?
Confirm the real surrender date, read the surrender and restoration clauses, and request a walkthrough. The office decommissioning checklist lists what to gather before it, the broom-swept move out checklist covers the handback, and the closing an office checklist covers the wider steps if the whole office is closing. The service itself is described on office decommissioning, and Phoenix-area projects on office decommissioning in Phoenix.
Get a timeline for your lease date
Call 602-703-4000 and ask for Tony, or email hello@officestation.com with your address, suite size and lease end date. Every project is quoted individually after the walkthrough.
Related questions
- What is office decommissioning?
- How to choose an office decommissioning company
- Office decommissioning vs junk removal
All of Office Station's planning guides are collected on office furniture resources.
Frequently asked questions
How long does office decommissioning take?
Plan on about 120 days from the first read of the lease to the landlord handback; the full lease exit commonly runs three to four months. The physical removal is much shorter: a typical floor with good dock and freight elevator access is often cleared in a few nights or a weekend. Office Station, based in Phoenix, Arizona and working nationwide, builds the schedule backward from your surrender date.
Can an office be decommissioned in 30 days?
Often, yes. Many offices can still exit cleanly with 30 to 45 days if decisions are made fast and the building cooperates. Below that you usually lose options: fewer contractors can commit, freight elevator slots are scarce and restoration work may push past the deadline. Night and weekend crews help compress the schedule.
What makes office decommissioning take longer?
Multiple floors, a server room or data closet, required cabling removal, restoration work on the landlord's list, strict building rules on elevator and dock times, and slow internal decisions about what moves and what goes. Late starts add delay of their own because building access gets booked by other tenants.
How long does the removal itself take?
For a typical office floor with good dock access, removal often takes a few nights or a weekend. Hardwired panel systems have to be disconnected by a licensed electrician first, and cabling comes out after the network is shut down, so those steps are sequenced into the removal week.
How soon can a walkthrough happen?
Office Station typically schedules a walkthrough within 48 hours of a request in Greater Phoenix and within two to three business days in other markets, and delivers a written recommendation within five business days. Call 602-703-4000 and ask for Tony.
When should we start planning an office decommission?
About 120 days before the surrender date, with a contractor selected by roughly day 60. Confirm the actual surrender date first, because some leases require notice to vacate months ahead or tie restoration to a walkthrough before the final day.